Alterations to EU procurement thresholds imminent
20/12/11

The financial thresholds which govern when a public works, service or supply contract should be advertised by a contracting authority in accordance with the Public Contracts Regulations 2006 (as amended) will be changing on 1 January 2012.


The new figures, all exclusive of VAT, have been converted from the fixed Euro amounts and are a slight increase on the existing thresholds. They are as follows:
 

 

   Services (£)  Supplies (£)  Works (£)
Entities listed in Schedule 1 (which includes NHS Trusts and Central Government Departments)
 113,057  113,057

 4,348,350

Other public sector contracting authorities (which includes Registered Providers)
 173,934  173,934  4,348,350

 


These new rates will apply to procurements commenced between 1 January 2012 and 31 December 2013.


Slight increases have also been made to the thresholds applicable to works covered by the Utilities Regulations and the Defence Procurement Rules.

 

« Back to News

 

 
download our newsletter
download our newsletter

LATEST NEWS

30/04/12
National Planning Policy Framework: Evolution not Revolution
Despite widespread calls from local authorities for 'transitionary arrangements', the National Planning Policy Framework (NPPF) came into force last month with immediate effect...
23/04/12
Changes to Riddor Regulations 2012
As of 6 April 2012, RIDDOR's over-three-day injury reporting requirement has changed...
BREEAM Award for St John’s Church Vicarage!
22/03/12
BREEAM Award for St John’s Church Vicarage!
Best Dwelling assessed under Code for Sustainable Homes achieving Level 6...
Housing Strategy Update
09/03/12
Housing Strategy Update
The headline to revive the Right to Buy was a cornerstone of the Housing Strategy – offering up to £50,000. However the Government recently revealed plans to raise the maximum discount to £75,000!
HSE Approve Cost Recovery Scheme Proposal Fee for Intervention Scheme (FFI)
09/03/12
HSE Approve Cost Recovery Scheme Proposal Fee for Intervention Scheme (FFI)
Andrew Shearman, Managing Director of calfordseaden Health & Safety, reports that FFI is now likely to be introduced in October 2012.
Digby Road, Hackney
09/03/12
Digby Road, Hackney
calfordseaden M&E and Sustainability teams worked with Network Housing Association and Archer Hoblin Construction to complete this new build scheme in one of the most deprived areas of Hackney.
Michael Whatford's Retirement
09/03/12
Michael Whatford's Retirement
Michael Whatford is Retiring at the end of March after 42 years in the Construction Industry.
Planning Granted for New Retirement Village
09/03/12
Planning Granted for New Retirement Village
Viridian Homes For Living, in partnership with the London Borough of Sutton, has received planning permission to redevelop and regenerate a sensitive site in a conservation area to provide a multi‑million pound retirement village in Cheam, Surrey.
This is Bromley South Central
09/03/12
This is Bromley South Central
calfordseaden are working with Cathedral on an urban opportunity site to provide project co‑ordination, quantity surveying and CDMC services in connection with the redevelopment of a site at the southern end of Bromley High Street, principally occupied by the Westmoreland Road car park.
Statutory Payment Terms
09/03/12
Statutory Payment Terms
1 October 2011 saw the introduction of a new set of statutory payment terms for construction contracts. Part 8 of the Local Democracy, Economic Development and Construction Act, 2009, which came into effect on that date, modifies and replaces the statutory terms that have been in operation since 1996.