calfordseaden are acting as client representative and contract administrator on behalf of the Trustees and Executive Committee of Gurdwara Sri Guru Singh Sabha (SGSS). We are also acting as the architect on the refurbishment of Norwood Hall situated on the site of the new school, and as monitoring surveyor to the funders.

 

SGSS, one of the leading Sikh institutions outside of India, has been given the responsibility of constructing Khalsa Primary School in Southall, London - the borough's first voluntary aided Sikh Primary School. 

 

calfordseaden prepared a design and obtained planning permission for the new school, then tendered the project using a traditional form of contract. However the priced tenders returned considerably exceeded the client's budget. calfordseaden were approach to advise on the project and look at ways of procuring the school within the budget.

 

A detailed review of the building specifications and contract arrangements was undertaken, revealing that considerable savings could be made by value engineering the specification and switching to a 'design and build' contract. In addition to the cost and contract issues, we worked closely with the community leaders to review certain aspects of the design. The aim was to ensure the building was tailored to the needs of the Sikh community.
 

Norwood Hall, a Grade II listed building, is being refurbished to provide opportunities for community activities. These works include both essential repairs to maintain the historic fabric of the house, and the alterations needed.


The project is currently on site and is due to receive pupils in September 2010, offering a two-form Primary school with nursery for 3-11 year olds, including 420 full-time primary places and 50 full-time nursery places, with 20 per cent of total places being reserved for children of other faiths.

 

The vision of the school, laid out by the Trustees and Executive Committee, includes providing pupils with an unrivalled National Curriculum education within the Sikh faith and culture, to build a strong community based on Sikh ethos.

 

For further information contact:

 

Teja Biring
at our London office
T 020 7940 3200 
E tbiring@calfordseaden.co.uk


 

 

« Back to News

 

 
download our newsletter
download our newsletter

LATEST NEWS

30/04/12
National Planning Policy Framework: Evolution not Revolution
Despite widespread calls from local authorities for 'transitionary arrangements', the National Planning Policy Framework (NPPF) came into force last month with immediate effect...
23/04/12
Changes to Riddor Regulations 2012
As of 6 April 2012, RIDDOR's over-three-day injury reporting requirement has changed...
BREEAM Award for St John’s Church Vicarage!
22/03/12
BREEAM Award for St John’s Church Vicarage!
Best Dwelling assessed under Code for Sustainable Homes achieving Level 6...
Housing Strategy Update
09/03/12
Housing Strategy Update
The headline to revive the Right to Buy was a cornerstone of the Housing Strategy – offering up to £50,000. However the Government recently revealed plans to raise the maximum discount to £75,000!
HSE Approve Cost Recovery Scheme Proposal Fee for Intervention Scheme (FFI)
09/03/12
HSE Approve Cost Recovery Scheme Proposal Fee for Intervention Scheme (FFI)
Andrew Shearman, Managing Director of calfordseaden Health & Safety, reports that FFI is now likely to be introduced in October 2012.
Digby Road, Hackney
09/03/12
Digby Road, Hackney
calfordseaden M&E and Sustainability teams worked with Network Housing Association and Archer Hoblin Construction to complete this new build scheme in one of the most deprived areas of Hackney.
Michael Whatford's Retirement
09/03/12
Michael Whatford's Retirement
Michael Whatford is Retiring at the end of March after 42 years in the Construction Industry.
Planning Granted for New Retirement Village
09/03/12
Planning Granted for New Retirement Village
Viridian Homes For Living, in partnership with the London Borough of Sutton, has received planning permission to redevelop and regenerate a sensitive site in a conservation area to provide a multi‑million pound retirement village in Cheam, Surrey.
This is Bromley South Central
09/03/12
This is Bromley South Central
calfordseaden are working with Cathedral on an urban opportunity site to provide project co‑ordination, quantity surveying and CDMC services in connection with the redevelopment of a site at the southern end of Bromley High Street, principally occupied by the Westmoreland Road car park.
Statutory Payment Terms
09/03/12
Statutory Payment Terms
1 October 2011 saw the introduction of a new set of statutory payment terms for construction contracts. Part 8 of the Local Democracy, Economic Development and Construction Act, 2009, which came into effect on that date, modifies and replaces the statutory terms that have been in operation since 1996.